WATER SUPPLY PLANNING COMMITTEE |
|||||
|
|
|||||
|
ITEM: |
ACTION ITEM |
||||
|
|
|||||
|
3. |
CONSIDER RECOMMENDATION
TO THE BOARD TO CONDUCT FIRST READING OF MALPASO WATER LLC ORDINANCE |
||||
|
|
|||||
|
Meeting Date: |
March 17, 2015 |
Budgeted: |
N/A |
||
|
|
|||||
|
From: |
David J. Stoldt, |
Program/ |
N/A |
||
|
|
General Manager |
Line Item No.: |
|
||
|
|
|||||
|
Prepared By: |
David J. Stoldt |
Cost Estimate: |
N/A |
||
|
|
|||||
|
General Counsel Review: N/A |
|||||
|
Committee Recommendation: N/A |
|||||
|
CEQA Compliance: N/A |
|||||
SUMMARY:
In 1997, Margaret and Clint Eastwood (Eastwood) canceled permits for
development of 82 homesites on the historic Odello East property, located on the south bank of the
Carmel River and primarily immediately east of Highway 1, and donated
approximately 49 acres of the 131 acre Odello East
and an agricultural water supply to the Big Sur Land Trust.
The
Eastwood still owns the remaining approximately 82 acres of Odello
East and are planning to donate this property to the Big Sur Land Trust to
facilitate the Carmel River Floodplain Restoration and Environmental
Enhancement Project ("Floodplain Project"). This property currently
is being used for irrigated pasture. After the donation is completed, the Big
Sur Land Trust will restore native vegetation on this property.
The
Odello East water rights will not be needed to
irrigate this property after native habitat is established. As envisioned by
the project proponents, eighty-five acre-feet per year of the Odello East water supply will be made available for community
benefits on existing lots of record within California American Water Company's
service area that is within the Carmel River watershed or the City of Carmel.
This water, for example, would allow for an existing home to be remodeled or
added on to, and for a new home to be built on an existing lot of record. Also,
this water could be used by Cal-Am on an interim basis to reduce Cal-Am's unauthorized
diversions from the Carmel River, consistent with the State Water Resource
Control Board (SWRCB) Cease and Desist Order. Forty-five acre-feet per year
(AFY) of the Odello East water supply will be
dedicated permanently to Carmel River instream use. This is structured to
provide beneficial use without adversely affecting water flows in the Carmel
River or water levels in the alluvial aquifer; and enhance flows to the Carmel
River Lagoon. The Eastwood donation of Odello East to
the Big Sur Land Trust will occur after final regulatory action to approve the
water rights assignment and the necessary agreements have been signed.
Bottlenecks
in the lower Carmel River from the construction of levees and Highway 1 have contributed
to significant floods. The 1995 flood destroyed the Highway 1 Bridge and the
1998 flood caused millions of dollars in damage to residents and businesses
north of the Carmel River. The Floodplain Project will let the river use its
floodplain by removing portions of the river levees, restoring the natural
floodplain on lower Odello East and building a
causeway to allow flood flows to pass under Highway 1 to the floodplain on the
west side of the highway. The original Floodplain Project included removal of
approximately 101,500 cubic yards of fill material on Odello
East (the "Blister" area), which blocked the Carmel River from
floodplain habitat. The Margaret Eastwood Trust removed the Blister in 2009 and
compacted it to create an east/west haul road on the property.
Removal of the Blister facilitates the Floodplain Project, and the haul road
can be used as a recreational trail through the donation to the Big Sur Land
Trust. Reconnecting the floodplain to the Carmel River and the Lagoon will
create and maintain a mosaic of wildlife habitats and aid in the restoration of
Steelhead. The recreational component of the project will include development
of an integrated trail and parkland system along the Carmel River.
The
County of Monterey is coordinating with public agencies for environmental
review for all phases of the Floodplain Project.
A
Memorandum of Understanding (MOU) Regarding Proposed Actions and Proposed
Process for Collaboration and Coordination on Community and Environmental
Benefits from Use of the Eastwood/Odello Water Right
was entered into on June 7, 2013 by and between California American Water
Company (Cal-Am) and the Margaret Eastwood Trust u/D/T dated
August 21, 1990 and Clint
Eastwood. The MOU calls for the following:
·
Eastwood
will form a limited liability company (LLC), for the purposes of holding and administering
water right License 13868A and entering into subscription agreements, as described
in the following paragraphs. The LLC is Malpaso Water LLC.
·
Eastwood
will file a petition with the SWRCB: (I) to split Eastwood's water-right License
13868 into two parts; (2) to add seven of Cal-Am's wells to the authorized
points of diversion (the points of diversion may change at the request of the
SWRCB) and to add the part of Cal-Am's service area that is in the Carmel
Valley watershed or the City of Carmel to the authorized place of use in one of
the licenses (which will be designated License 13868A); and (3) to assign this
new license to the LLC.
·
Eastwood
will work with the SWRCB to prepare an environmental impact report on Eastwood's
petition. The SWRCB will certify the final EIR.
·
The
other license (which will be designated License 13868B) will be for the remainder
of License 13868. This license will be for approximately 45 AFY of instream use.
·
Eastwood
will request the Monterey Peninsula Water Management District (MPWMD) to adopt
a new rule, similar to Rule 23.5 (which was used for the Pebble Beach
subscription agreements), under which the District will issue water use permits
to the parcel owners who have entered into subscription agreements with the
LLC. The proposed ordinance to adopt the
new rule is attached as Exhibit 3-A.
·
The
LLC will enter into subscription agreements with owners of legal lots of record
in the areas of use. The subscription
agreements and water-use permits issued by MPWMD will run with the land and
will not be transferable.
·
Eastwood
and Cal-Am will enter into a water supply conveyance and temporary water transfer
agreement.
·
Eastwood's
will ask the SWRCB to confirm that SWRCB Order WR 2009-0060 (as modified by
Order WR 2010-0001) does not prohibit Cal-Am from diverting and conveying water
under the Eastwood LLC's water-right License 13868A to Eastwood's subscribers.
·
Cal-Am
will seek a modification of CPUC Decision 11-03-048 to clarify that the moratorium
ordered by the Decision does not apply to connections to Cal-Am's system by
Eastwood's subscribers.
·
After
the SWRCB, the CPUC and the MPWMD have taken the necessary regulatory actions,
Cal-Am will convey and deliver water to Eastwood subscribers that have received
water-use permits from the MPWMD, and Cal-Am will provide any necessary new
meters and connections for such subscribers. After these regulatory actions
have occurred, Cal-Am will use any available surplus under License 13868A to
divert water from the Carmel Valley aquifer through the wells designated as
points of diversion in License 13868A and to supply the diverted water to its
existing customers in the Carmel River watershed or the City of Carmel. MPWMD has requested that to the extent such
water is surplus to the legally available supplies from other Cal-Am sources, the
Odello East water be made available to the Aquifer
Storage and Recovery system.
EXHIBIT
3-A Proposed Ordinance
U:\staff\Board_Committees\WSP\2015\20150317\03\Item
3.docx