3 MGD at Sand City |
Desalination facility: $29.2 million
Cal-Am facilities: $9.0-13.4 million
TOTAL: $38.2-42.6 million |
Seasonal operation: $2.1 million
Full-time operation: $2.8 million |
|
6 MGD at Sand City |
Desalination facility: $53.2 million
Cal-Am facilities: $12.7-17.9 million
TOTAL: $65.9-71.1 million |
Seasonal operation: $3.9 million
Full-time operation: $5.4 million |
|
7-14 MGD at MRWPCA or Moss Landing sites |
Desalination facility: $72.0-171.3 million
Cal-Am facilities: $13.4-19.4 million
TOTAL: $85.4-190.7 million (rounded)
(see Section A.4 for detailed cost information) |
Seasonal operation: $4.6-9.3 million
Full-time operation: $6.4-12.9 million |