EXHIBIT 2-A
MONTEREY PENINSULA WATER
MANAGEMENT DISTRICT
MEMORANDUM
DATE: March
3, 2010
TO: Darby
Fuerst, General Manager
FROM: Andrew
M. Bell, District Engineer
SUBJECT: Work Plan and Schedule to Identify Potential Desalination Project Sites Located within the MPWMD Boundary
SUMMARY
Based
on direction given by the Water Supply Planning Committee members at their
February 2, 2010 meeting, following is a work plan and schedule for identifying
potential desalination projects within the MPWMD boundary.
TASKS AND ESTIMATED
SCHEDULE
1. Develop Feasibility Criteria March
31, 2010
a. In consultation with Water Supply Planning
Committee, establish water supply goals and feasibility criteria for desal
projects within the District.
2. Literature Search
April 16, 2010
a. Review
MPWMD reports to determine what sites have been identified and investigated (completed - see Jan. 25, 2010 memo,
b. Assemble
geologic maps of MPWMD coastline to allow identification of potential locations
of feedwater intake.
3. Field Surveys
April 30, 2010
a. Visit all sites that appear may have
potential.
4. Meet with Agencies and Property Owners
May 14, 2010
a. Likely
meetings:
1. Cities of
2.
3. National Marine Sanctuary
b. Possible
meetings:
1. Cities of
2.
3. Pebble Beach Company
5. Analyze Information Collected and Prepare
Report on Findings June 30, 2010
a. Review information collected.
b. Prepare conceptual project designs and
cost estimates for each site identified.
c. Prepare report of findings, including
assessment of feasibility of each site.