ADMINISTRATIVE COMMITTEE

 

6.

CONSIDER APPROVAL FOR GRAnt funding for Hastings Reservation Ford RePLACEMENT ON Finch Creek

 

Meeting Date:

February 13, 2020

Budgeted: 

Yes

 

From:

David J. Stoldt

Program/

ERD/Fisheries

 

General Manager

Line Item No.:

2-3-9

 

 

 

 

Prepared By:

Beverly Chaney

Cost Estimate:

$100,000

 

General Counsel Approval:  N/A

Committee Recommendation:  The Water Supply Planning Committee reviewed this item twice: once on March 28, 2019 and a second time on February 5 and recommended approval. Administrative Committee reviewed this item on February 13, 2020 and recommended _____________.

CEQA Compliance:  This grant is exempt as defined by the California Environmental Quality Act Guidelines section 15301(i). Project permitting will be handled by UCB.

 

SUMMARY: Finch Creek, in upper Carmel Valley, is the primary tributary to Cachagua Creek, and is potentially one of the most productive, highest habitat value creeks downstream of Los Padres Dam. In normal and above water years, much of Finch Creek remains wetted, allowing steelhead to survive the summer and contribute to the overall success of the Carmel River watershed’s steelhead population.

 

The wet stream crossing (ford) at UC Berkeley’s (UCB) Hastings Natural History Reservation on Finch Creek was identified as a likely steelhead barrier with “inadequate passage” and was ranked 6th worst in the District’s 2014 Steelhead Barrier Assessment Report – part of the Integrated Regional Water Management (IRWM) report the District completed in 2014. Removal of this barrier would allow unrestricted passage to an additional 3.5 miles of quality stream habitat in wet years. Work to remove other barriers further downstream is currently being undertaken by Trout Unlimited and their partners. While this site is outside the District boundary, it is in the Carmel River Watershed and within the Integrated Regional Water Management (IRWM) boundary.

 

The concept of a partnership between the District, UCB/ Hastings Reserve, and the State Coastal Conservancy (SCC) to fund the planning, permitting and construction of a replacement crossing on Finch Creek to improve steelhead passage was brought before the District’s Water Supply Planning Committee for discussion in March 2019.  Dr. Jennifer Hunter, Hastings’ Director, gave a presentation and after a discussion and questions, the Committee gave its support to a District grant to help fund the project.

 

By the end of 2019, both UCB and the SCC were ready to move forward with the project. They need the grant money from the District to stay on-track this spring with the planning and permitting stage. Construction is planned for fall of 2020 with possible project completion by the end of this year.

 

RECOMMENDATION:  Recommend that the Board of Directors authorize the General Manager to approve the grant to the Regents of the University of California, Berkeley campus, for the work related to the replacement of the Finch Creek Ford at the Hastings Natural History Reservation for a not-to-exceed amount of $100,000. 

 

IMPACT TO STAFF/RESOURCES:  Funds for this project are included in the FY 2019-2020 budget under “Aquatic Resources Fisheries” line item 2-3-9 Ford Removal @ Hastings Reservation”, Account 24-04-785870, $100,000.

 

EXHIBIT

6-A      Proposal from Regents University of California, Hastings Reservation, Finch Creek Ford Replacement Grant Request dated December 19, 2019.

 

 

 

U:\staff\Board_Committees\Admin\2020\20200213\06\Item-6.docx