ITEM: |
INFORMATIONAL
ITEM/STAFF REPORT |
||||
|
|
|||||
|
20. |
MONTHLY WATER SUPPLY AND CALIFORNIA AMERICAN WATER
PRODUCTION REPORT |
||||
|
|
|||||
|
Meeting Date: |
November 17, 2025
|
Budgeted:
|
N/A
|
||
|
|
|||||
|
From: |
David J. Stoldt, |
Program/ |
N/A |
||
|
|
General Manager |
Line Item No.: |
|||
|
|
|
|
|||
|
Prepared By: |
Jonathan Lear |
Cost Estimate: |
N/A |
||
|
|
|||||
General Counsel
Review: N/A
|
|||||
Committee
Recommendation: N/A
|
|||||
|
CEQA Compliance:
Exempt from environmental review per SWRCB Order Nos. 95-10 and 2016-0016,
and the Seaside Basin Groundwater Basin adjudication decision, as amended and
Section 15268 of the California Environmental Quality Act (CEQA) Guidelines,
as a ministerial project; Exempt from Section 15307, Actions by Regulatory
Agencies for Protection of Natural Resources. |
|||||
Exhibit 20-A shows
the water supply status for the Monterey Peninsula Water Resources System
(MPWRS) as of November 1, 2025. This system includes the surface water
resources in the
Water Supply Status:
Rainfall through November 2025
totaled 1.11 inches and
brings the cumulative rainfall total for WY 2026 to 1.11 inches, which is 149%
of the long-term average through October. Estimated unimpaired runoff through October totaled 335 acre-feet (AF)
and brings the cumulative runoff total for WY 2026 to 335 AF, which is 84% of the long-term average through October. Usable storage for the MRWPRS was 30,560 acre-feet, which is 111% of average through October, and equates to 92% of system capacity.
Production Compliance: Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 3,376 AF of water from the Carmel River in WY 2026. Through October, using the CDO accounting method, Cal-Am has produced 232 AF from the Carmel River (excluding 0 AF of Table 13 and 7 AF of Mal Paso.) In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,474 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2026. Through October, Cal-Am has produced 124 AF from the Seaside Groundwater Basin. Through October, 0 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, 0 AF have been diverted under Table 13 water rights, and 413 AF of Pure Water Monterey recovered. Cal-Am has produced 790 AF for customer use from all sources through October. Exhibit 20-B shows production by source. Some of the values in this report may be revised in the future as Cal-Am finalizes their production values and monitoring data.
EXHIBITS
20-A Water Supply Status: Nov
1, 2025
20-B Monthly Cal-Am production by source: WY 2025
U:\staff\Boardpacket\2025\111725\Informational
Items\20\Item-20.docx