| EXHIBIT 6E | |
| Aquifer Storage and Recovery | |
| Estimated Costs of 2nd Well | |
| Bid preparation and support | $10,000 |
| Construction management | 70,000 |
| Summary report | 15,000 |
| C-57 contractor | 750,000 |
| Army lease amendment | 10,000 |
| Total | $855,000 |
| Additionally, it is estimated that $500,000 of improvements | |
| would need to be made to the Cal-Am distribution | |
| system to maximize efficiency of the new well. | |