ITEM:

DISCUSSION  ITEMS

 

22.

AUTHORIZE EXPENDITURE OF UNBUDGETED FUNDS FOR PURE WATER MONTEREY PROJECT DESIGN BID PACKAGES

 

Meeting Date:

November 16, 2015

Budgeted: 

N/A

 

From:

David J. Stoldt

Program/

 

 

General Manager

Line Item No.:    

 

Prepared By:

David J. Stoldt

Cost Estimate:

 

 

General Counsel Approval:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  N/A

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SUMMARY:  A schedule for the Phase 2 proceedings at the CPUC, the consideration of the Pure Water Monterey groundwater replenishment project (GWR), was requested through a joint motion by the parties as follows:

 

Date

Phase 1 (Desalination)

Phase 2 (Pure Water Monterey)

December 15, 2015

Supplemental testimony with updated costs concerning the desalination project

 

January 22, 2016

Supplemental testimony on demand and supply, brine discharge and return water

Testimony on Phase 2

January/February

Phase 1 settlement discussions

Phase 2 settlement discussions

March 22, 2016

Concurrent rebuttal testimony

Concurrent rebuttal testimony

April  14- 15, 2016

Evidentiary hearings for Phase 2 and on Phase 1 updates

Evidentiary hearings for Phase 2 and on Phase 1 updates

May 2016

Continued Phase 1 settlement discussions;

Continued Phase 2 settlement discussions until May 15;

Opening Brief on Phase 2

May 2016

 

Reply Brief on Phase 2 (2 weeks following opening brief)

July 2016

 

Target for Phase 2 Proposed Decision*

August 2016

 

Target for Commission action on Phase 2 decision*

TBD

CPUC’s issuance of combined Draft EIR/EIS

 

TBD

Comments on Combined DEIR/DEIS

 

15 days after close of DEIR/DEIS Comment Period

Opening Legal and Policy Brief

 

30 days after close of DEIR/DEIS Comment Period

Reply Legal and Policy Brief

 

 

The schedule has not been yet approved by the Administrative Law Judge, but if it is, then by July it is possible that Pure Water Monterey has been approved by the CPUC to move forward.

 

In order to be ready to do so, the contracts for design for design-bid components and preparation of bid packets for construction manager at risk (CMAR) components need to be put into place.  MRWPCA is preparing the relevant requests for qualifications for public release at this time with awards expected in early December.

 

This is an acceleration of the timeline for these contracts.  As such, very few of their related costs were budgeted in the current fiscal year GWR budget.  These contracts are expected to require approximately $3.6 million, of which $400,000 is in the budget.  That leaves $3.2 million unfunded, approximately 75% of which is likely to occur in the current fiscal year, or $2.4 million.  The District’s cost-sharing agreement would result in $1.8 million of additional need.

 

RECOMMENDATION:  The General Manager recommends the Board authorize expenditure of unbudgeted funds for contracts for design-bid components and preparation of bid packets for construction manager at risk (CMAR) components.

 

DISCUSSION:  The District has not yet identified a revenue source for this expenditure.  Staff expects that this amount could derive from four sources: (i) savings in the current year budget for the District’s public financing of desalination due to the schedule delays on the Environmental Impact Report; (ii) other savings from mid-year budget review; (iii) reserves; and (iv) a favorable ruling by the California Supreme Court on its November 3, 2015 hearing of the User Fee litigation.  It is not expected that a commitment to fund these costs will deplete the District’s reserves.  The District General Manager and CFO will commit to regular monitoring of the expenditures in order to ensure that activities be delayed or put on hold prior to imperiling District reserves.

 

EXHIBIT

None

 

 

U:\staff\Boardpacket\2015\20151116\ActionItems\22\Item22.docx