EXHIBIT 15-D
Monterey Peninsula Water Management District
Mid-Year Budget Adjustment-Project Expenditures
2011-2012 Budget
Original Amended
Division Description Budget Adjustment Budget
WRD 1-2-1 A1 g, Facility building equipment 181,000 66,500 247,500
WRD 1-2-1 A1 h, Contingency (10%) 52,500 6,600 59,100
WRD 1-2-1 A2 c, Electrical power 18,000 12,000 30,000
WRD 1-2-1 A2 f, Contingency (10%) 11,300 2,100 13,400
WRD 1-2-1 A3 a, Well No. 1 interim piping connection to Santa Margarita site 27,500 17,500 45,000
WRD 1-2-1 A3 d, Contingency (15%) 8,700 2,700 11,400
WRD 1-2-1 B1 d, Well No. 1 PG&E electrical 33,500 4,500 38,000
WRD 1-2-1 B1 f, Well No. 1 MCWD water connection 22,000 (19,000) 3,000
WRD 1-2-1 B1 h, Well No. 1 temporary security fencing 2,700 14,300 17,000
WRD 2-3-1 A, General operations and maintenance 46,900 (22,300) 24,600
WRD 2-3-1 B, Power 58,500 (24,100) 34,400
WRD 2-3-1 D, Replacement of standby generator fuel 2,800 (1,000) 1,800
WRD 2-3-2 A,  Miscellaneous fish rescue supplies 2,500 (1,000) 1,500
WRD 2-3-2 C,  Seasonal Fish Rescue Workers 14,800 (5,400) 9,400
WRD 2-3-2 F, On-call fish rescue crew 3,200 (600) 2,600
WRD 2-3-3 A,  Smolt rescue supplies 0 1,000 1,000
WRD 2-3-4 A,  San Clemente Dam fish counter supplies 500 1,400 1,900
WRD 2-3-5 Adult & kelt rescue and transport 0 300 300
PED 1-3-1, MPWMD Desalination 150,000 (125,000) 25,000  
PED 2-1-2 B, Riparian corridor maintenance projects 1,500 (1,000) 500
PED 2-1-4 Address vegetation hazards and remove trash from channel 18,000 (7,000) 11,000
PED 2-6 A, Update IRWM Plan Chapters 1-15 56,100 (16,100) 40,000 [2]
PED 2-6 B, Update to the Canyon Del Rey Drainage Plan 330,000 (270,000) 60,000 [2]
WRD 2-6 C, Salt and nutriant management plan for the SGB  75,000 (25,000) 50,000 [2]
WRD 2-6 D, Assessment of steelhead passage barriers 65,000 (59,000) 6,000 [2]
PED 2-6 G, Assessment for San Joe Creek watershed  60,000 (60,000) 0 [2]
PED 2-6 H, ASBS alternatives analysis  270,000 (200,000) 70,000 [2]
PED 2-6 J, Feasibility of Scenic Road preservation  0 20,000 20,000 [2]
PED 2-8-1, Permit processing assistance 15,000 (9,000) 6,000 [3]
PED 2-8-2, Hydrogeologic impact review 12,000 (5,000) 7,000 [3]
PED 2-8-3, County fees - CEQA posting and recording 10,000 (4,000) 6,000 [3]
PED 2-8-4, Technical procedures update 2,000 5,000 7,000 [3]
GMO 3-1-1, Annual newsletter 20,000 (15,000) 5,000
 
WDD 4-1-1 B, Tolling of water credits EIR 50,000 (50,000) 0
WDD 4-2-1 D, Water Efficiency Training/Education (Public) 33,000 (23,000) 10,000 [4]
WDD 4-2-2 A, Landscape auditors 300,000 (200,000) 100,000 [4]
WDD 4-2-2 B, School retrofit grant program 150,000 100,000 250,000 [4]
WDD 4-2-2 D, Conservation printed material 5,000 (3,000) 2,000 [4]
WDD 4-2-2 F, Conservation devices 20,000 15,000 35,000 [4]
WDD 4-2-2 H, Rainwater/graywater demonstration projects 20,100 (20,100) 0 [4]
WDD 4-2-2 I, Best management practices 2,500 2,500 5,000 [4]
WDD 4-2-3 A,  CAW Rebate 600,000 (400,000) 200,000 [1]
WDD 4-2-3 C,  Non-CAW (MPWMD funded) 30,000 (15,000) 15,000
       Total $2,781,600 ($1,309,200) $1,472,400
[1]  CAW rebates funding deferred due to pending resolution of GRC
[2]  IRWMD Grant agreement not finalized until Dec 2011
[3]  Direct bill - adjustments are made to the revenues
[4]  CAW reimbursements - adjustments are made to the revenues