FINAL for 3/27/08 Meeting MPWMD Comparative Matrix, Part II, Desalination Projects
DECISION ELEMENT Seawater Conversion Vessel 
PROPONENT/SPONSOR Water Standard Company
PROJECT DESCRIPTION Completely self contained seawater desalination treatment plant installed on a ship. Electrical energy and propulsion will be provided by gas turbine engines fueled with Biodiesel.  No seabed intake or outfall lines are required.  Water produced on the ship will be  shuttled to shore as required.
Facilities required to distribute the water to customers on shore are unknown at this time but could be assumed to be similar to those required in the other alternatives. Size of project is unknown but assumed to be 20 MGD (approx. 22,000 AFY). Costs provided for 18 MGD project yield (approx. 20,000 AFY).
Pilot Project None planned. State currently requires pilot plants but that requirement was written around land based facilities. WSC sees no need to pilot the process since we have over 2,000 ships currently successfully treating seawater. Issues needs to be discussed with the State DOHS.
PROJECT YIELD 10 MGD - 75 MGD.  Actual yield to be based on commitments of purveyor customers
Comply with Order 95-10? Water for Seaside Basin? Yes, and can easily meet all future needs
Future Monterey Peninsula Needs? Could easily be sized for all future needs
Future Non-Monterey Peninsula Needs Could easily be sized for all future needs
TOTAL YIELD Could easily be sized for all future needs
Yield Phasing to Monterey Peninsula Phasing will be based on demands. Larger size initially is better.
PROJECT COST Costs in 2006-2007 dollars for 18 MGD (approx 20,000 AFY) project provided by WSC
Capital - see lines 77-106 $168,290,000 for 18 MGD SCV (with power plant). Distribution improvements unkown.  B-E/GEI: $185,620,000
Amortized Cap. Cost ($/yr) Information not provided  B-E/GEI: $14,960,000
O&M - see lines 108-112 $16,262,000 using subsidized fuel.  B-E/GEI:  $16,260,000 (subsidized fuel) - $20,850,000 (unsubsidized fuel)
Assumed energy cost ($/kwh) $0.05 / kwh (using Biodiesel with current US government rebate tax incentive)
Total Annual Cost Information not provided  B-E/GEI:  $31,220,000 (subsidized fuel) - $35,810,000 (unsubsidized fuel)
Time frame for estimates 2006 - 2007  B-E/GEI: 2007
COST TO PENINSULA
Share of total project cost
How share determined
Cost sharing of existing vs. future Cal-Am ratepayers
Cost of Water ($/AF) Cost of water produced on the SCV estimated to be less than $1,000 AF.  Costs for required distribution and pumping unknown.  B-E/GEI:  $1,550 (subsidized fuel) - $1,770 (unsubsidized fuel).  Based on 18 MGD yield (approx. 20,000 AFY).
Impact to Cal-Am Bill N/A
FINANCING ASSUMPTIONS WSC funding can be used. Prefer a public private partnership with MPWMD
Interest rate (%) 80% at 7% interest and 20% at 12% if private, 7% if municipal.        B-E/GEI: 7%
Term (yrs) 20 years if private, 30 yrs if municipal.  B-E/GEI: 30 years
Public vote required?
Grants (describe) Office of Emergency Services or other Homeland Security funding should be looked into. WSC has not done that.
TIMELINE
Draft EIR (and/or EIS) No actions taken on CEQA activities
Certify FEIR (EIS ROD)
Obtain key permits None applied for at this time
Secure financing Upon municiapl agency approval
Secure ROW/property access NA for SCV
Start construction Information not provided
Commence water delivery 3 years after contractual arrangements
Total time to water delivery 3 years after contractual arrangements
PERMITS/REGS
Federal Agencies Same as land based facility except Coast guard must review operational plans.
EIS needed?
Fed lead agency? To be determined, if needed.
Sanctuary approval? Permit will be required. Not applied for yet.
State Agencies Same as any land based treament plant
CPUC approval? N/A 
EIR lead agency MPWMD
SWRCB/Water Rights N/A
Regional Agencies None required for SCV
Monterey County None required for SCV
Local Agencies None required for SCV. Distribution system requiores construction and use permits within affected jurisdictions
SITE CONTROL
Confirmed site? Location doesn’t really matter for the SCV itself. Shuttle ship off loading site must be selected depending on who the customers are.
Alternative sites and projects? No restrictions. No land required. SCV can be located anywhere.
OPERATIONS/OTHER
Technical, Managerial and Financial Capabilities (TMF) to meet DHS standards Assume implementing entity would operate desal plant with MPWMD oversight.
Back-up; water production interruptions (e.g., power or intake water) Redundant treatment equipment per State codes; back-up gas turbine planned
PROJECT PARTICIPANTS
Overview Willing to expand plant to meet needs of others such as FORA, MCWD and Monterey Peninsula. Shuttle ship concept may allow cities up and down the coast to participate.
MPWMD participation MPWMD currently envisioned as sole sponsor.
Other entities participation None specified; partnerships possible.
PUBLIC INVOLVEMENT
Outreach programs Presentations by WSC to MPWMD, CCC, MBNMS, community groups, and others
INFORMATION SOURCES Materials submitted by WSC and PBS&J
CAPITAL COST DETAIL Year 2006-2007 costs  
DESALINATION (assume 18 MGD facility)  
Intake Included in SCV cost
Pre-treatment Included in SCV cost
Desal Plant Ship cost with retrofitting/conversion cost is $66,400,000 + $49,0200,000 for all PALL process equipment  B-E/GEI:  Ship cost incl. feed and brine disposal - $73,000,000.  Desalination process equip. - $64,000,000
Post-treatment Included in SCV cost
Brine discharge Included in SCV cost
Storage Unknown
Transmission Pipelines Seabed & distribution pipelines: $45,370,000  B-E/GEI:  $48,620,000
Pump stations SCV seawater intake PS included
Energy facilities 2 gas turbines included in Desal Plant cost (most desal plants do not include a power plant)
DESAL SUBTOTAL $168,290
ASR COSTS N/A
RECYCLED WATER COSTS N/A
OTHER WATER SOURCES N/A
ADDL CAPITAL COSTS
Pilot Plant Need has to be resolved with State Department of Health
Distribution system improvements None identified
Right-of-way N/A for SCV
Envtl review, permits, etc. Unknown
Engineering Included in above categories (Engineering, OH, Legal, & Admin. Costs total $18,810,000)  B-E/GEI:  $28,740,000
Construction Management Included in above categories
Admin/legal Included in above categories
Mitigation measures N/A for SCV
Contingencies $32,560,000 (included in above categories)  B-E/GEI:  $37,120,000
SUBTOTAL Included in above categories
TOTAL CAPITAL COST Capital costs for SCV are $168,290,000.(including the power plant).  CAW distribution system costs are unkown at this time.      B-E/GEI: $185,620,000
ANNUAL O&M COST DETAIL
Energy Included in total O&M
Facilities O&M Included in total O&M
Mitigation O&M N/A
TOTAL O&M ($/yr) $16,262,000 using subsidized fuel.  B-E/GEI:  $16,260,000 (subsidized fuel) - $20,850,000 (unsubsidized fuel)
SOURCES FOR COSTS Capital and O&M costs were provided by WSC and PBS&J based on detailed estimates from V Ship, Pall Corp, GE Energy.  Seawater Desalination Projects Evaluation, B-E/GEI Consultants, February 20, 2008
ACRONYMS
$/AF cost per acre-foot
$/kwh- cost per killowatt-hour
ac acre
AFY acre-feet per year
ARB Air Resources Board
ASR aquifer storge and recovery
B-E/GEI Bookman-Edmonston/GEI Consultants
BRAC Base Realignment and Closure Office (US Army)
BRDEIR Board Review Draft EIR on MPWMD Water Supply Project (Dec 2003)
Cal-Am California American Water 
CalTrans California Dept. of Transportation
CAW California American Water 
CCC California Coastal Commission
CDFG California Dept. Fish & Game
CDM Camp Dresser & McKee Inc.
CDPH California Dept. of Public Health
CDTS California Dept. of Toxic Substances
CEC California Energy Commission
CEQA California Environmental Quality Act
COP Certificate of Participation
CPCN Certificate of Public Convenience and Necessity
CPUC California Public Utilities Commission
CR Carmel River
CSD Community Services District
CWP Coastal Water Project
DBO design-build-operate
DEIR Draft EIR
DPR California Dept. of Parks & Recreation
Duke Duke Energy Corporation
DWR California Dept. of Water Resources
EIR Environmental Impact Report
EIS Environmental Impact Statement
FEIR Final EIR
FORA Fort Ord Reuse Authority
HDD horizontal directionally-drilled
IS Initial Study
JPA Joint Powers Authority
K/J Kennedy Jenks Engineers, Inc.
MBNMS Monterey Bay National Marine Sanctuary
MBUAPCD Monterey Bay Unified Air Pollution Control District
MCEH Monterey County Environmental Health
MCPBI Monterey County Dept. Planning & Building Inspection 
MCPW Monterey County Public Works
MCWD Marina Coast Water District
MCWRA Monterey County Water Resources Agency
MLHD Moss Landing Harbor District
MLML Moss Landing Marine Laboratory
MLPP Moss Landing Power Plant
MoCo Monterey County
MP Monterey Peninsula 
MPWMD Monterey Peninsula Water Management District
MRWPCA Monterey Regional Water Pollution Control Agency
N/A not applicable
NEPA National Environmental Policy Act
NMCDP North Monterey County Desalination Project
NOAA Fish National Marine Fisheries Service (part of Natl Oceanic and Atmospheric Administration)
NOP Notice of Preparation
NorCo North Monterey County
O&M operations and maintenance
PEA Proponent's Environmental Assessment
P/SM Pajaro/Sunny Mesa Community Services District
RBF RBF Consulting, Inc
ROD Record of Decision
ROW right-of-way 
RWQCB Regional Water Quality Control Board
SHPO State Historic Preservation Office
SLC State Lands Commission
SRF State Revolving Fund, a loan administered by SWRCB 
SWRCB State Water Resources Control Board
TAMC Transportation Agency of Monterey County
TBD to be determined
USACOE US Army Corps of Engineers
USBLM US Bureau of Land Management
USBR US Bureau of Reclamation
USCG US Coast Guard
ESEPA US Environmental Protection Agency
USFWS US Fish & Wildlife Service
CG US Coast Guard
SCV Seawater Conversion Vessel
WSC Water Standard Company
PBS&J Post, Buckley, Schuh & Jernigan, Inc.
V Ships V Ships, Inc.
Pall Pall Corporation